Monticello MN Data Center Construction Timeline & Phase Breakdown (2026–2029 Update)

monticello mn data center construction timeline

Monticello MN Data Center Construction Timeline & Phase Breakdown

The Most Detailed 2026–2029 Timeline Publicly Available (Updated November 29, 2025)

PROJECT 1: Microsoft / Frattalone Companies – 3 Million sq ft Campus

Location: 300+ acres along Highway 25, Monticello (former Sherco coal plant buffer land)
Total Power Load: 400+ MW (one of the largest single-site loads in Minnesota history)
Expected Groundbreaking: April–June 2026
Full Build-Out Horizon: 2029–2031 (six 500,000 sq ft buildings delivered in sequence)

PHASE 1 – Site Preparation & Critical Infrastructure

Q2 2026 – Q4 2026 (9 months)

PHASE 2 – Buildings 1 & 2 Shell & Core

Q1 2027 – Q1 2028 (12–14 months)


PHASE 3 – Mechanical, Electrical & Plumbing (MEP) Fit-Outs

Q2 2028 – Q4 2028 (9–12 months)
The longest-lead and most lucrative phase for skilled trades:

PHASE 4 – Buildings 3–6 + Final Campus Amenities

2029 – 2031

PROJECT 2: Scannell Properties / Xcel Energy – 1.3 Million sq ft “Monticello Tech Park”

Location: Former Monticello Nuclear Generating Plant site
Tenant: Widely expected to be another hyperscaler (Google, Meta, or Oracle rumored)
Expected Groundbreaking: Q3 2026 – Q1 2027
First Buildings Online: Late 2028


PHASE 1 – Demolition & Remediation

COMPLETED 2024–2025

PHASE 2 – New Infrastructure & Substation

Q3 2026 – Q2 2027

PHASE 3 – First Two Buildings (750,000 sq ft total)

Q3 2027 – Q4 2028

PHASE 4 – Final Building (550,000 sq ft)

2029–2030




400+ MW of new power coming online – one of the biggest loads in Minnesota history

THE OVERLAP:
2027–2028 Will Be Absolute Peak

Both campuses hit full stride at the same time.
Combined on-site workforce at peak: 1,500–2,200+ workers simultaneously.
Monticello becomes one of the three or four largest construction zones in the entire Upper Midwest for two straight years.

TRADE-BY-TRADE DEMAND FORECAST (2026–2029)

WANT TO GET ON THE SHORTLIST BEFORE THE RUSH HITS?

General contractors and staffing agencies are quietly building their databases right now.
Register your company or crew in under 30 seconds and get notified the minute new bid packages drop.

FULL 2026–2029 MILESTONE CALENDAR

LATEST OFFICIAL UPDATES (November 2025)